Strand seawall and promenade, Phase 2
A new seawall and promenade at Strand: Mosterd’s Bay is open again, the rest due in February 2027.

Photo Credit
Image courtesy of © SkyPixels · CC BY-SA 4.0 via Wikimedia CommonsThe second phase of the Strand seawall runs from the Strand Pavilion to Greenways, with an upgraded wall, a universally accessible promenade and new beach access points. In November 2026 the city opened the promenade and beach at Mosterd’s Bay for the summer; the Haarlem Street to Greenways stretch reopens after works finish, with completion planned for February 2027.
Strand’s long beach on False Bay runs right beside Beach Road, and the wall between them is being rebuilt from end to end. The second phase of its rebuild is now most of the way there, and this summer the first new stretches of promenade are open to walk.
The new wall
Phase 1, from Da Gama Street to the Strand Pavilion, is already finished. Phase 2 continues from the Pavilion to Greenways: an upgraded seawall, a universally accessible promenade, new beach access points and traffic calming with raised intersections on Beach Road. The wall itself arrives in pieces, as prefabricated L-shaped concrete units, topped with curved cope units.
Five stages, piece by piece
The city split Phase 2 into five stages of roughly five months each. By June 2025, 36 wall units had been set in place, with 90 more and over 300 cope units made and waiting on site. The method is simple to describe and slow to do: dig out the beach, cast the foundations, crane in the wall, then put the sand back as if nothing had happened.
What lies beneath
The work is not only about the view. Several sewer lines run under the beach, and the city says the new wall protects them, along with the new services and road behind it. It is the rare piece of coastal engineering whose main beneficiaries will never see the sea.
Open this summer
On 20 November 2026 the city said the promenade and beach at Mosterd’s Bay, between the Strand Municipal Swimming Pool and Haarlem Road, would be open, along with the beach between Adshade Road and Jackson Black, reached by new access points from the promenade. Beach Road between the pool and Haarlem Road is back to two-way traffic with parking.
A seawall built in L-shaped pieces, partly to protect sewers nobody will ever see. Engineering rarely gets a better view.
Still to come
The promenade between Haarlem Street and Greenways stays closed for now. The city expects the seawall itself to be finished before the builders’ break on 10 December 2026.
Work then resumes on 11 January, with completion planned for February 2027. When the second phase began, the city expected to finish in November 2026; on a coast where the sea sets the schedule, three months is a modest overrun. Until then that stretch of Beach Road runs one way, towards Cape Town.
Getting there
Southbound traffic is diverted along Haarlem Street, a temporary public car park serves the one-way section and the Haarlem Street car park is partly open. The car park beside the swimming pool stays in use as a works yard for now. Beachfront homes and businesses remain reachable throughout.
Questions and answers
Is Strand beach open during the seawall works?
Yes, in part. From late November 2026 the promenade and beach at Mosterd’s Bay and between Adshade Road and Jackson Black are open; the Haarlem Street to Greenways promenade stays closed until works finish.
When will the Strand seawall be finished?
The city expects the wall itself before 10 December 2026 and the whole of Phase 2 by February 2027.
Why it's on our list
- Universally accessible promenade
- Mosterd’s Bay promenade open for summer 2026
- Completion planned February 2027